Certificate of Company Registration & Certificate of Commencement of Business were received from Office of Company Registrar (OCR) on July 29, 2010 & August 29, 2011 respectively.
Survey License for Power Generation received from Ministry of Energy on April 8, 2011.
Connection Agreement for power evacuation was done with NEA on August 25, 2011 and Power Purchase Agreement (PPA) was signed on November 14, 2011.
Tripartite Loan Agreement between was signed between EPF, CHCL and the company on December 8, 2011
The project started construction by February 11, 2014 and targeted to complete the project by the end of December 2020.
Consulting services is awarded to Tractebel Engineering GmbH( formerly Lahmeyer Internation GmbH(LI)) in association with TMS.
Detailed Project Report has been completed.
Hydrological measurements at headworks and powerhouse site is being continued.Surface geological investigation including drilling in headworks and powerhouse as well as sub-surface exploration with HRT has been carried out to determine the geological condition in the key structure locations.
Land acquisition process is in Final Stage of completion.
Test Adit is completed by Himal Hydro Construction Ltd.
Camp Facilities are constructed.
Diversion Tunnel Constructed by Himal Hydro Construction Ltd.
EIA approved 12 th November 2013
Generation License received December 03, 2013
Lot-1 (Civil and Hydromechanical works) contract is awarded to Guangxi Hydroelectric Construction Bureau.
Lot2 Electro-Mechanical Contract is Awarded to Andritz Hydro Private Limited in association with Trade Link International.
Transmission Line works Contract is Awarded to Urja-AC JV Lalitpur, Nepal on July 27, 2018.
IEE of Transmission Line approved on May 23, 2019 (2076/02/09)