Type of Project: |
Run-of-River (ROR) |
Design flow: |
50.8 m3/sec |
Gross Head: |
235 m |
Headworks: |
Gated Weir Type with Undersluice and Side Intake |
Desanding Basin Type & Size: |
Surface, 100 m(l) x 13 m(w) x 8.5 m(h) |
Tunnel Length & Size: |
7124 m x 5.7 m(w) x 5.7 m(h) |
Powerhouse Type & Size: |
Surface Powerhouse 52 m(l) x 15 m(b) x 25.5 m(h) |
Turbine: Unit Capacity: |
Type, Orientation & Number Francis, Vertical Axis & 3 Nos. 34 MW
|
Generator Unit Capacity & Nos.: |
40 MVA & 3 Nos. |
Installed Capacity: |
102 MW (3 x 34 MW) |
Annual Salable Energy: |
542.2 GWh |
Dry Energy: |
83.7 GWh |
Wet Energy: |
458.5GWh |
Transmission Line Length/ Voltage: |
4 km/Single Circuit 220 kV |