I heartily welcome all the visitors to MBJCL Web Site. It is our effort to provide related information about MBJCL activities to all using online media as soon as possible. Please don't forget to make your comments and suggestions to make this website more fruitful and efficient.

Madhya Bhotekoshi Jalavidyut Company Limited (MBJCL) is a subsidiary company of Chilime Hydropower Company Limited, registered as public company in july 2010. MBJCL has planned to develop Middle Bhotekoshi Hydroelectric Project (MBKHEP) with an installed capacity of 102 MW in Sindhupalchowk district of Central Development Region.Tri-partite loan agreement has been signed between EPF, Chilime and MBJCL for debt portion. The equity investment will be made through 51% promoter share and 49% public share. Chilime is a leading company with 37% share.

Introduction

Madhya Bhotekoshi Jalavidyut Company Limited (MBJCL) is a subsidiary company of Chilime Hydropower Company Limited, registered as public company in july 2010. MBJCL has planned to develop Middle Bhotekoshi Hydroelectric Project (MBKHEP) with an installed capacity of 102 MW in Sindhupalchowk district of Central Development Region.
Tri-partite loan agreement has been signed between EPF, Chilime and MBJCL for debt portion. The equity investment will be made through 51% promoter share and 49% public share. Chilime is a leading company with 37% share.

Read More
Project: Introduction
Type of Project: Run-of-River (ROR)
Design flow: 50.8 m3/sec
Gross Head: 235 m
Headworks: Gated Weir Type with Undersluice and Side Intake
Desanding Basin Type & Size: Surface, 100 m(l) x 13 m(w) x 8.5 m(h)
Tunnel Length & Size: 7124 m x 5.7 m(w) x 5.7 m(h)
Powerhouse Type & Size: Surface Powerhouse 52 m(l) x 15 m(b) x 25.5 m(h)
Turbine:
Unit Capacity:

Type, Orientation & Number
Francis, Vertical Axis & 3 Nos. 34 MW

Generator Unit Capacity & Nos.: 40 MVA & 3 Nos.
Installed Capacity: 102 MW (3 x 34 MW)
Annual Salable Energy: 542.2 GWh
Dry Energy: 83.7 GWh
Wet Energy: 458.5GWh
Transmission Line Length/ Voltage: 4 km/Single Circuit 220 kV


Copyright © 2010-2022 Madhya Bhotekoshi Jalavidyut Company Limited.
Nabil Bank, Tower, 1st Floor, Maharajgunj, Kathmandu, Nepal, P.O.Box: 23599, Phone: +977-1-4721641, +977-1-4721642 , Fax: +977-1-4721643,
Email: admin@mbjcl.com.np

FIND US ON SOCIAL NETWORK :           CHAT : 

1 This site as been visited 1002773 times.

Check Mail